Due to further failures of generation units, power utility Eskom has escalated load shedding from Stage 2 to Stage 4 on Thursday.
The power utility had implemented Stage 2 load shedding on Monday after seven units lost generating capacity over the weekend.
Currently, unplanned breakdowns at power stations amount to some 15 439 MW of lost power with at least 5505MW of planned outages underway.
In a statement, Eskom said at least four units ran into challenges on Tuesday evening – necessitating the need to escalate the severity of load shedding.
Read more:
#POWERALERT1
— Eskom Hld SOC Ltd (@Eskom_SA) March 9, 2022
Due to further failures of generation units, Stage 4 loadshedding will be implemented from 09:00 today until 05:00 on Friday in order to manage the emergency reserves pic.twitter.com/OMmqjLKIUX